Citizens Oversight Committee to Meet March 20, 2014

The Citizens Oversight Committee to meet Thursday, March 20, 2014 at 12 noon, IVC Board Room...

Career Technical Facilities 81% Complete

Construction for the Career Technical Facilities project continues and is approximately 81% complete! November 2013 Progress Update Work Completed Building 3100:...

Career Technical Facilities 63% Complete

Construction for the Career Technical Facilities project continues and is approximately  63% complete! August 2013 Progress Update Work Completed Building 3100: ...

Career Technical Project – Construction Update

Construction for the Career Technical project continues and is approximately 58% complete! July 2013 Progress Update Work Completed Building 3100: Work...

900 BUILDING MODERNIZATION ACHIEVES 92% LOCAL PARTICIPATION!

The modernization of the 900 building is underway to support the campus’s business and data processing needs.    The improvements will...